Now what? Years of permitting and success in court wiped away on appeal.

Grain Belt Express is a $7 billion electric transmission infrastructure project connecting four states—Kansas, Missouri, Illinois, and Indiana—across 800 miles. An Invenergy Transmission project, Grain Belt Express will carry more affordable, reliable power to millions of homes and businesses across the Midwest and other regions, delivering 100% domestic, clean electricity while powering economic opportunity and energy security

The moral of the story is that big transmission takes a long time to route and permit. In that time, needs change and new technologies can emerge. It was a challenge yesterday and looks to be a challenge in the years to come.

Solutions anyone? I like:

  • HVDC underground
  • shared use of existing civil transportation corridors like highways, canals and railroads.
  • offering a small percentage of the annual project revenue to adjacent private landowners for their “buy in”